In Earned Value Management (EVM), what is the standard mathematical formula for calculating the Schedule Performance Index (SPI)?
In Earned Value Management (EVM), what is the standard mathematical formula for calculating the Schedule Performance Index (SPI)?
Multiple Choice Options
- A✓ Correct Option
- B
- C
- D
Detailed Technical Solution & Explanation
In EVM, the Schedule Performance Index () measures schedule efficiency:
. An indicates ahead of schedule, while indicates project delays. ( is the Cost Performance Index, ).
Option Analysis:
•
Option A (SPI = ): Correct. Standard EVM formula for schedule efficiency.
•
Option B (SPI = ): Inverted formula.
•
Option C (SPI = ): Inverted cost ratio.
•
Option D (SPI = ): Formula for Cost Performance Index ().