AALL10 · Chapter 10Project Planning & Implementation🏛️ Past Licensure QuestionID: f533954c
In engineering project cost management, what is the standard formula used to compute a 'Cost Overrun'?
In engineering project cost management, what is the standard formula used to compute a 'Cost Overrun'?
Multiple Choice Options
- A✓ Correct Option
- B
- C
- D
Detailed Technical Solution & Explanation
A cost overrun (or budget overrun) is the excess amount by which the actual costs incurred exceed the baseline budgeted/planned cost:
.
Option Analysis:
•
Option A (\text{Cost Overrun} = \text{Actual ...): Correct. Standard definition of cost overrun.
•
Option B (\text{Cost Overrun} = ft(\frac{\...): Describes percentage expenditure index, not monetary overrun.
•
Option C (\text{Cost Overrun} = \text{Planned...): Total budget contingency, not overrun.
•
Option D (\text{Cost Overrun} = \text{Total C...): Direct costs, not overrun.
Reference: Demo2 · Set 2NEC Licensure Syllabus