In project schedule optimization, 'Resource Smoothing' is defined as:
In project schedule optimization, 'Resource Smoothing' is defined as:
Multiple Choice Options
- A✓ Correct Option
An adjustment of activity schedules within their available float such that the predetermined project completion date is NOT delayed
- B
Adding overtime shifts to reduce total project duration
- C
Eliminating non-critical path activities
- D
Decreasing budget contingency reserves
Detailed Technical Solution & Explanation
Resource Smoothing is a resource optimization technique that adjusts activity start and finish dates strictly within their free and total float limits so that the project completion date is not delayed.
Option Analysis:
•
Option A (Adjust schedules within float without delaying completion date): Correct; defines resource smoothing.
•
Option B (Adding overtime to reduce duration): Defines project crashing.
•
Option C (Eliminating activities): Scope reduction.
•
Option D (Decreasing reserves): Cost management decision.
Reference: Mock Test 06NEC Licensure Syllabus