Process that involves continuously improving and detailing a plan as more detail become available is termed as
Process that involves continuously improving and detailing a plan as more detail become available is termed as
Multiple Choice Options
- A
project analysis
- B
project enhancing
- C
progressive deliberation 7
- D✓ Correct Option
progressive elaboration
Detailed Technical Solution & Explanation
According to standard engineering principles, for Process that involves continuously improving and detailing a plan as more detail become available is termed as, the correct choice is progressive elaboration.
Option Analysis:
•
Option A (project analysis): Incorrect. Does not satisfy the technical condition or specifies an alternate/invalid property.
•
Option B (project enhancing): Incorrect. Does not satisfy the technical condition or specifies an alternate/invalid property.
•
Option C (progressive deliberation 7): Incorrect. Does not satisfy the technical condition or specifies an alternate/invalid property.
•
Option D (progressive elaboration): Correct. Valid technical statement directly addressing the question requirement.