Which of the following statements regarding CPM network analysis is/are INCORRECT?
(i) Earliest start of an activity is the early event time of the node it leaves.
(ii) Latest finish of an activity is the late event time of the node it enters.
(iii) Latest start of an activity is its latest finish minus its duration.
Which of the following statements regarding CPM network analysis is/are INCORRECT?
(i) Earliest start of an activity is the early event time of the node it leaves.
(ii) Latest finish of an activity is the late event time of the node it enters.
(iii) Latest start of an activity is its latest finish minus its duration.
Multiple Choice Options
- A
Only (i)
- B
(i) and (ii)
- C
(ii) and (iii)
- D✓ Correct Option
None
Detailed Technical Solution & Explanation
Let us verify each proposition in CPM event-oriented network analysis:
•
Statement (i): An activity cannot start until its tail event occurs. Therefore, Earliest Start Time () equals the Early Event Time of node (). Correct.
•
Statement (ii): An activity must finish by the time head event occurs. Therefore, Latest Finish Time () equals the Late Event Time of node (). Correct.
•
Statement (iii): By definition, Latest Start Time equals Latest Finish Time minus activity duration (). Correct.
Since all three statements are fundamentally correct, none of them are incorrect.
Option Analysis:
•
Option A (Only (i)): Incorrect; statement (i) is correct.
•
Option B ((i) and (ii)): Incorrect; both statements (i) and (ii) are correct.
•
Option C ((ii) and (iii)): Incorrect; both statements (ii) and (iii) are correct.
•
Option D (None): Correct; none of the given statements are incorrect.