Free float for any project activity is defined as the difference between:
Free float for any project activity is defined as the difference between:
Multiple Choice Options
- A
Its latest start time and earliest start time
- Bโ Correct Option
Its earliest finish time and earliest start time for its successor activity
- C
Its latest finish time and earliest start time for its successor activity
- D
Its earliest finish time and latest start time for its successor activity
Detailed Technical Solution & Explanation
Free float represents the surplus duration available for an activity such that its completion does not delay the earliest possible start of any succeeding activity. Mathematically:
Where is the earliest start time of the succeeding activity and is the earliest finish time of the current activity.
Option Analysis:
โข
Option A (Its latest start time and earliest start time): Defines Total Float ().
โข
Option B (Its earliest finish time and earliest start time for its successor activity): Correct; precisely describes Free Float.
โข
Option C (Its latest finish time and earliest start time for its successor activity): Erroneous combination.
โข
Option D (Its earliest finish time and latest start time for its successor activity): Erroneous combination.